This potential future project involves the removal of 3,130 feet of existing levee along the left bank of the Carbon River and the construction of a new armored levee set back to the west and south , potentially encompassing an area of approximately 124 acres to increase flood protection. The project is currently in the feasibility study phase and is anticipated to be completed by second quarter of 2021.

Carbon River Setback Levee project link: https://piercecountywa.gov/6340/Carbon-River-Levee